Things are starting to finally come together. The exterior of the 4 unit building is just about complete. Sidewalks should be coming shortly, along with finishing the porch railing on the left end Augusta unit #7. We are also starting to wrap up the finishing touches on the interior in the next few weeks and will follow up with those photos once things are complete.
The Colonial unit 8 and Sawgrass unit 9 have drywall completed and are or will be painted very soon. The Colonial has Hardwood and Tile floors installed. A buyer, for at least the immediate future, would be able to make some choices on the finish carpeting and cabinetry but that window is closing soon.
The Sawgrass unit 9 Hardwood and Tile will be installed in the next two weeks and the kitchen and bathroom cabinets for have been ordered. Finished carpet flooring could still be selected by a buyer.
The detached Garages for the Colonial and Sawgrass will also be starting soon as well and should not take much time to get up and under roof.