Spring has finally arrived here in Happy Valley and construction on our Pine Hall 4 unit townhouse is finally making progress.
The framing has been completed and a majority of the electrical and plumbing rough-ins is complete for most of the units.
Sewer depths have allowed us to add a basement bath rough-in for a future use in each unit. If you will need more living space, you could add up to an additional 700 to 1,000 Square Feet.
We can now start working on the exterior of the units to give them a finished look . We should be starting the siding within the next week and have the stone and brick work scheduled to follow that up.
We will soon be working on the interior of one of the end units as we will be using that as a model home to show the finishes that will be included with the units.
Please check back in a few weeks to see updated photos along with a progress update.